OVERVIEW AWARDS

The number of electrified villages reached 349, and a total of 18,455 high-voltage plants, 31,957 low-voltage plants, and 12,960 service plants were completed. The length of high-voltage overhead lines laid reached 4,717 kilometers, and the length of low-voltage overhead lines laid 7,049 kilometers, the number of transformers installed and accepted reached 471, and the number of household electricity meters installed reached 31,010.


The project has brought light to 88,000 households in 772 villages in Ghana and is of great significance in promoting the full realization of national electrification in Ghana. During the implementation, HCIG actively trained the working skills of local workers, bringing nearly thousands of jobs to the local area, and the electricity in the village indirectly created thousands of jobs as well.